FS#14277 — Racks G125A08
Attached to Project— Datacenters
Maintenance | |
Gravelines | |
CLOSED | |
![]() |
Summary: We have detected a default on the fex public which requires rebooting
Actions: Restart Switch.
Start: Tuesday December 20th starting at 6:00 AM
Affected racks: G125A08
Impact: Disconnection of the public network during the reboot
Estimated time: 15 min
Date: Tuesday, 20 December 2016, 06:06AMActions: Restart Switch.
Start: Tuesday December 20th starting at 6:00 AM
Affected racks: G125A08
Impact: Disconnection of the public network during the reboot
Estimated time: 15 min
Reason for closing: Done