FS#14286 — Room G105 and G115

Attached to Project— Datacenters
Maintenance
Gravelines
CLOSED
100%
Summary: We detected a defect on the cooling system of these rooms.
Actions: Replacing the defective part
Start: Monday 26 December 2016 at 10H00 Paris time
Affected rack: G105% and G115%
Impact: None, the cooling circuit is doubled.
Estimated time: 1h
Date:  Monday, 26 December 2016, 15:05PM
Reason for closing:  Done
Additional comments about closing:  Done
Comment by OVH - Monday, 26 December 2016, 10:33AM

Intervention is started


Comment by OVH - Monday, 26 December 2016, 14:09PM

Intervention still ongoing