FS#1435 — FS#5430 — P19 : maintenances HT and BT

Attached to Project— Datacenters
Maintenance
Paris 19
CLOSED
100%
We will carry out a series of maintenances on the electric
power supply of our data centre Paris19.

Today and tomorrow, the maintenances will be done on the high tension,
then on the main circuit breaker of the low tension distribution.
Date:  Thursday, 12 May 2011, 07:45AM
Reason for closing:  Done
Additional comments about closing:  Maintenances have revealed some minor problems which are going to be corrected.

Installations have been maintained, every rescue system is tested and validated.