FS#14391 — Room 31
Attached to Project— Datacenters
Maintenance | |
Roubaix 2 | |
CLOSED | |
![]() |
Summary : Following a previous maintenance on the cooling of the room, we must check the correct functioning of the last modifications.
Actions : Check cooling system.
Start : Thursday 23 February 2017 at 10.00AM CET
Affected Rack : room 31
Impact : None
Estimated Time : 4 hours
Date: Monday, 20 March 2017, 13:05PMActions : Check cooling system.
Start : Thursday 23 February 2017 at 10.00AM CET
Affected Rack : room 31
Impact : None
Estimated Time : 4 hours
Reason for closing: Done
We start the check of the cooling system.
The verification is almost complete, but it remains one point to check. This last point will be made tomorrow from 10:00