FS#14391 — Room 31

Attached to Project— Datacenters
Maintenance
Roubaix 2
CLOSED
100%
Summary : Following a previous maintenance on the cooling of the room, we must check the correct functioning of the last modifications.
Actions : Check cooling system.
Start : Thursday 23 February 2017 at 10.00AM CET
Affected Rack : room 31
Impact : None
Estimated Time : 4 hours
Date:  Monday, 20 March 2017, 13:05PM
Reason for closing:  Done
Comment by OVH - Thursday, 23 February 2017, 11:24AM

We start the check of the cooling system.


Comment by OVH - Thursday, 23 February 2017, 17:34PM

The verification is almost complete, but it remains one point to check. This last point will be made tomorrow from 10:00