We will be re-organizing rack 051014 tomorrow between 1pm and 4pm SGP time. Servers will be moved progressively, around an hour of downtime is expected from the moment servers are turned off.
We will update this thread throughout the task.
Update(s):
Date: 2017-02-28 07:39:12 UTC Migration completed
Date: 2017-02-28 07:36:50 UTC sgp1-sdtor3-2k migration completed all servers are back online.
Date: 2017-02-28 06:47:50 UTC Carrying on with sgp1-sdtor3-2k, the servers in the following IP range will be going down momentarily.
139.99.8.97 - 139.99.8.144
Date: 2017-02-28 06:15:35 UTC sgp1-sdtor2-2k migration completed all servers are back online.
Date: 2017-02-28 04:57:42 UTC sgp1-sdtor1-2k migration completed all servers are back online.
Carrying on with sgp1-sdtor-2k, the servers in the following IP range will be going down momentarily.
139.99.8.49 - 139.99.8.96
Date: 2017-02-28 03:50:21 UTC We are starting the migration of sgp1-sdtor1-2k servers in the following IP range will be going down momentarily.