FS#14471 — Room 46M%

Attached to Project— Datacenters
Maintenance
Roubaix 6
CLOSED
100%
Summary : We will intervene on the Cooling System of thoses rooms
Actions : Intervention on the cooling system
Start : Thursday March 30th starting at 10:00 AM
Affected Rack : 46M01 to 46M09
Impact : None
Estimated Time : None, this task will be updated regularly
Date:  Friday, 31 March 2017, 19:17PM
Reason for closing:  Done
Comment by OVH - Thursday, 30 March 2017, 10:10AM

We are starting the intervention.


Comment by OVH - Thursday, 30 March 2017, 16:34PM

We have completed the first part of the system.
The second part will be finished tomorrow.

The room is currently cooled.


Comment by OVH - Friday, 31 March 2017, 19:16PM

Second part is now finished