FS#14585 — 46L14 46L15 46L16 46L17 46L18 46L19

Attached to Project— Network
Modernization
Roubaix → RBX-6
CLOSED
100%
Summary: In order to improve the quality of our systems, we will replace the power supplies of the network equipment of these racks.
Actions: Replacement of the network equipment power supplies.
Start: 19/05/17 starting at 06:00 AM
Affected: 46L14 46L15 46L16 46L17 46L18 46L19
Impact: No impact, all network equipment are redundant.
Estimated time: 2h
Date:  Friday, 19 May 2017, 08:04AM
Reason for closing:  Done