FS#14829 — Room 45 and room 46

Attached to Project— Datacenters
Modernization
Roubaix 3
CLOSED
100%
Summary : In order to improve the high tension power supply securisation, we will put in production a rescue transformer.
Actions : Put in production a rescue transformer
Start : Thursday july 7th starting at 09:00 UTC+2
Affected Rack : all racks in room 45 and room 46
Impact : None, we do not operate on the production infrastructure
Estimated Time : 04h
Date:  Thursday, 13 July 2017, 13:05PM
Reason for closing:  Done
Comment by OVH - Thursday, 06 July 2017, 17:07PM

We change the schedule date to thursday july 13th.


Comment by OVH - Thursday, 13 July 2017, 13:05PM

The rescue transformer is in production.