FS#14951 — gra-3a/b-6k

Attached to Project— Network
Modernization
GRA-1
Planned
0%
We will add some capacity between gra-3a/b-6k and gra-d1/d2-a75 :

- 4 x 10 G between gra-3a-6k <=> gra-3a-n9
- 4 x 10 G between gra-3b-6k <=> gra-3b-n9
- 40 G between gra-3a-n9 <=> gra-d1-a75
- 40 G between gra-3a-n9 <=> gra-d2-a75
- 40 G between gra-3b-n9 <=> gra-d1-a75
- 40 G between gra-3b-n9 <=> gra-d2-a75

The operation is planned the 17th of August 01:00AM (UTC). No impact expected during the operation.