FS#14999 — fra-1-a9 / fra-1-n7 and vie-1-6k

Attached to Project— Network
Maintenance
Whole Network
CLOSED
100%
We will upgrade those equipment in the latest versions recommended.
The objective is to improve the management of memory parity errors (soft correction) and allow the implementation of new features and new hardware support during the coming next year on these equipment.

No impact is expected, both equipment will be isolated before maintenance, and traffic will flow to other peering points.

We plan to do this maintenance on Tuesday 29th of August at 01:00am (UTC).

Weathermap: http://weathermap.ovh.net/#frankfurt
Date:  Tuesday, 29 August 2017, 03:49AM
Reason for closing:  Done
Comment by OVH - Tuesday, 29 August 2017, 02:30AM

We are going to start the maintenance. We first isolation the equipment before the upgrade. We will isolate the Vienne router too.

Then we will upgrade fra-1-a9.


Comment by OVH - Tuesday, 29 August 2017, 03:11AM

Done.

We are going to upgrade fra-1-n7


Comment by OVH - Tuesday, 29 August 2017, 03:35AM

Done.

We put them back to production