Get webhook notifications whenever Network & Infrastructure creates an incident, updates an incident, resolves an incident or changes a component status.
We will upgrade those equipment in the latest versions recommended.
The objective on the n77 is to allow the implementation of new features and new hardware support during the coming next year on this equipment. On the ASR9k, the objective is to fix the bug on the NP of the linecards.
Both equipment will be isolated before maintenance, and traffic will flow to other peering points.
The following services will be impacted by this maintenance:
> Housing of Global Switch will be isolated,
> VOiP (Service will be re-routed to the PoP of TH2),
> vRack Connect without redundant link (located at Equinix PA3 and Global Switch Datacenter),
> CDN (Traffic will be re-routed to other CDN infrastructure all over Europe).
We plan to do this maintenance on Wednesday 6th of December at 01:00am (UTC).
Date: 2017-12-06 03:21:51 UTC The linecard from the slot 7 has been upgraded. We are now checking both equipment and we will put back them in production.
Date: 2017-12-06 02:56:05 UTC The linecard from the slot 8 and 9 have been upgraded. We continue
Date: 2017-12-06 02:36:31 UTC The linecard from the slot 10 has been upgraded. We continue
Date: 2017-12-06 02:25:33 UTC The EPLD on the supervisors have been upgraded. We will upgrade now the linecards
Date: 2017-12-06 02:01:04 UTC The Nexus has been upgraded. We are now upgrading the EPLD of it
Date: 2017-12-06 01:53:25 UTC The ASR router is up to date. We are verifying if there is no issue during the upgrade.
Date: 2017-12-06 01:46:41 UTC Both equipment are isolated. We are upgrading them
Date: 2017-12-06 01:14:23 UTC We are going to start the maintenance