FS#1982 — FS#5961 — EG/MG network switch
Attached to Project— Dedicated servers
Maintenance | |
RBX4 | |
CLOSED | |
![]() |
We are going to change the kind of switch on a part of the servers
of the datacenter of Roubaix4 (n5010 to n5548).
We start tomorrow morning between 6 and 8 with the following networks :
46.105.104.0/24
46.105.105.0/24
46.105.110.0/24
46.105.111.0/24
A 2 minutes interruption is expected.
Date: Thursday, 20 October 2011, 12:05PMof the datacenter of Roubaix4 (n5010 to n5548).
We start tomorrow morning between 6 and 8 with the following networks :
46.105.104.0/24
46.105.105.0/24
46.105.110.0/24
46.105.111.0/24
A 2 minutes interruption is expected.
Reason for closing: Done
Additional comments about closing: This part of the maintenance task was finalised.
We have got another case of figure to do on other networks during the coming days, but this part was finished.
Switching completed for the networks below:
46.105.104.0/24
46.105.105.0/24
46.105.110.0/24
46.105.111.0/24
We will switch the network today
46.105.106.0/24
46.105.107.0/24
46.105.108.0/24
46.105.109.0/24
2-4 minutes of crashes are predicted by network