We planned changing telephony routers as an anticipation of future upgrades.
Routers come to their full capacity, we will change the chassis in order to add new cards.
The telephony infrastructure is connected to both routers, we will switch all traffic to one of them while changing the other.
The calls will keep operating during this operation.
Once the router is switched, we will switch back to the new router to finish the operation.
At this moment,a cut of the calls in progress is be expected.
The beginning of the operation is scheduled for Tuesday, January 24 at 4:00am.
Update(s):
Date: 2012-02-02 13:12:43 UTC The 2 routers are working normally.
Date: 2012-02-02 13:09:37 UTC The router is operational again on the new chassis. We are fixing the last cabling problems which are impacting some machines of the infra.
Date: 2012-02-02 13:08:20 UTC The cards are inserted in the new chassis which restarting is in progress.
Date: 2012-02-02 13:07:42 UTC The working started. We interrupted the p19-v2 to switch on the new chassis.
Date: 2012-02-01 18:09:25 UTC The switch of V2 router will finally take place that night (01-02/02). Work will start from about 1:00 CET. We will replace the chassis of p19-v2 as for the p19-v1.
Date: 2012-01-24 05:39:29 UTC The latest links are being reconnected on v1. We reported switching v2 tomorrow. We will optimize the operation of rewiring.
Date: 2012-01-24 05:38:16 UTC Rewiring is still in progress. The operation seems logner than we expected.
Date: 2012-01-24 05:37:29 UTC The new chassis v1 is being rewired.
Date: 2012-01-24 05:36:53 UTC We are restarting on the new chassis.
Date: 2012-01-24 05:36:26 UTC We will cut traffic on the router p19-v
Date: 2012-01-24 02:58:48 UTC We finished the final preparations to switch to the router p19-v2.