OVHcloud Network Status

Current status
Legend
  • Operational
  • Degraded performance
  • Partial Outage
  • Major Outage
  • Under maintenance
FS#6416 — Paris backbone work - 23-24/02
Scheduled Maintenance Report for Network & Infrastructure
Completed
We work tonight on the backbone in Paris for the establishment of two new routers on globalswitch and th2: gsw-g16a9 and th2-g1-a9. These two routers will become the main nodes of Paris through which traffic between the directions of Roubaix/P19/Madrid/Frankfurt/Lyon/Bordeaux/Strasbourg will be routed.

These new equipments will allow us to upgrade the links Paris <> Roubaix with additional 8x10G initially which will bring the capacity Paris <> Roubaix to 280G in total.

The routers will be included step by step on the backbone. Traffic to Paris, Lyon and Madrid will be impacted during the migration of different links. We start the work from 23:30.


Update(s):

Date: 2012-02-24 09:39:07 UTC
Links Paris <> Roubaix are upgraded. We fix the remaining problems on some lambdas.



Date: 2012-02-24 09:38:03 UTC
gsw-g1-a9<>mad-1 UP
gsw-g1-a9<>bor-1 UP

Date: 2012-02-24 09:37:48 UTC
th2-g1-a9<>p19-2 UP
th2-g1-a9<>p19-7 UP
th2-g1-a9<>fra-5 UP
th2-g1-a9<>sbg-3a UP

Date: 2012-02-24 09:37:34 UTC
gsw-g1-a9<>p19-2 UP
gsw-g1-a9<>p19-7 UP
gsw-g1-a9<>mad-5 UP
gsw-g1-a9<>lyo-1 UP

Date: 2012-02-24 09:37:11 UTC
gsw-g1-a9 <> th2-5 UP
th2-g1-a9 <> gsw-1 UP

We start the migration of links to p19.

Date: 2012-02-24 09:36:32 UTC
gsw-g1-a9 <> th2-1 UP
th2-g1-a9 <> gsw-2 UP

Date: 2012-02-24 09:36:09 UTC
th2-g1-a9 <> rbx-g1-a9 UP
th2-g1-a9 <> rbx-g2-a9 UP

Date: 2012-02-24 09:35:43 UTC
gsw-g1-a9 <> rbx-g1-a9 UP
gsw-g1-a9 <> rbx-g2-a9 UP

Date: 2012-02-24 09:35:19 UTC
gsw-g1 <> gsw-1 UP
gsw-g1 <> gsw-2 UP
th2-g1 <> th2-1 UP
th2-g1 <> th2-5 UP

We start the migration of links to roubaix on the new links.

Date: 2012-02-24 09:34:13 UTC
We start the intervention.
Posted Feb 24, 2012 - 09:33 UTC