FS#7648 — Switzerland
Scheduled Maintenance Report for Web Cloud
Completed
We start testing interconnection with Swisscom.

These tests will be done on an infrastructure dedicated for testing and isolated
the infra from the production.

The tests will be conducted in several phases.

The first phase will last between 2 and 3 weeks. It allows operators to validate
the respect of equipment telecom standards that will be used in production.


Update(s):

Date: 2012-12-21 14:03:30 UTC
Swisscom has validated interconnection tests.

Date: 2012-12-13 12:09:57 UTC
Interconnection tests went well. Swisscom teams are analysing the results.

Date: 2012-11-23 15:23:06 UTC
SS7 signaling tests were successfully.

The protocol compatibility of SS7 equipment is validated by swisscom.

We will continue testing with them next week to validate the compliance
of local telecom standards.
Posted Nov 19, 2012 - 11:50 UTC