Get webhook notifications whenever Network & Infrastructure creates an incident, updates an incident, resolves an incident or changes a component status.
Following a dramatic increase in the network traffic in the last weeks from the Beauharnois site, we've decided to add 10x10G of capacity between BHS and Newark. Capacity upgrades are expected to be operational on November 21st.
Furthermore, in January, 2015, we will start deployments of optical equipment in order to light 500G of capacity between Beauharnois and Newark.
Update(s):
Date: 2014-12-05 13:34:01 UTC We added 40G between Newark and Beauharnois.
We work with our supplier to troubleshoot the last links.
Date: 2014-11-24 16:09:55 UTC We are still awaiting the delivery of our lines from the supplier. The date is now for December 14, 2014.
Date: 2014-10-30 16:33:20 UTC We are going to add 2 x 10G between Beauharnois and Newark.The total capacity between these 2 POPS is currently 120G.