Get webhook notifications whenever Network & Infrastructure creates an incident, updates an incident, resolves an incident or changes a component status.
To improve the quality and the reliability of routing for HG2010 networks, we will switch this function from vss-1 and 2 on new routers dedicated solely to this task (rbx-s3-s4-6k and rbx-6k).
There is no anticipated impact on the traffic.
The first concerned network is 188.165.13.
Update(s):
Date: 2011-01-14 12:05:44 UTC The switch is over.
Date: 2011-01-14 12:05:20 UTC We start the switch routing network 188.165.15.
Date: 2011-01-06 12:03:20 UTC The migration of the last network 188.165.15 is ongoing. The machines were moved. We will switch the routing to the new infra tonight (from 06 to 07).
Date: 2010-12-16 09:44:44 UTC The migration of the network 188.165.12 was finalised.
Date: 2010-12-16 09:44:15 UTC 4 machines are to be migrated tonight, still on the network 188.165.12. We will switch the routing without a break.
Date: 2010-12-15 00:09:49 UTC We start the switching of the latest network machines 188.165.12.
Date: 2010-12-14 10:19:34 UTC We have finished last night the migration of the major party of the machines of 188.165.12 network. The concerned customers were informed, as for the other interventions, individually by email. There remains 6 servers to switch next night (14/12 starting from 23:00) then we will switch the network routing to the new routers (rbx-s3/s4).
Date: 2010-12-14 10:14:46 UTC During the switch of this night, the routing of some ip failovers was interrupted on the network 188.165.14. The problem is fixed now.
Date: 2010-12-10 08:35:17 UTC We will finish this night the changeover of the network 188.165.14 with the routing switch on the new infra
Date: 2010-12-10 08:28:15 UTC The switch of 188.165.13 is in progress